Building a frame house
Frame houses
Frame house construction is 215 m2.
The total area of the building is 215 m2. The dimensions of the building are 17 x 11 m. The building is two-story, the second floor - attic. Foundations are made of monolithic reinforced concrete. Walls are wooden frame with mineral wool insulation. Floors of the first floor on the ground; Wooden overlays.
General view of the house.
On the ground floor are: garage, boiler room, bathroom 9m2, hallway 13 m2, kitchen area of 15 m2, living room 27 m2, bedroom or office room 14.5 m2.
Ground floor plan.
On the second floor there are three bedrooms, a billiard room, a dressing room and two bathrooms.
Plan of the second floor.
The task is to build a house until spring
The project was completed in September. While the estimates compiled, the equipment had expired for some time.
Beginning of construction work. October.
Underground part of the foundation is ready. From the spot of the house, the soil-vegetative layer is taken away for further use. Installation of formwork for the cap is carried out.
Monolithic concrete plinth is ready. The space under the floor is covered with coarse-grained river sand, sliced with water and is gradually trimmed. The base is ready for laying the heater and floor laying on the soil.
General view of the foundation in the process of placing horizontal waterproofing. The top of the socle is covered with bituminous-polymeric waterproofing "sporlimod".
During the concreting in the base, threaded studs with a diameter of 12 mm are installed. There is installation of a lower binding of two boards in the thickness of 50 mm.
It remains to know:
How to build a house
General view of the foundation in the process of installing the lower strap on the top of the cap.
Installation of a wooden frame of the first floor began. The frame is made of wooden boards 50 x 150 mm. Boards dry, humidity 22% and treated with antiseptic. To give the stability of the rack unfastened by temporary diagonals.
Filling concrete floor base. Concrete is a layer of foam plastic 150 mm. Concrete screed reinforces a grid of 100 x 100 mm. In the place of the collision of concrete and wooden elements laid waterproofing of polyethylene film.
November.
The first snow fell, but the frame mounting does not stop.
The ground floor frame is ready.
However, an unforeseen delay in the delivery of dry forest occurred during the construction process. In order not to lose time, the OSB board and windproof film began to lining the frame.
General view of the house during the installation of the frame.
In parallel with the installation of racks of the carcass of the second floor, installation of rafters is carried out.
framework of the frame.
A general view of the location of the racks in the corner of the building. All elements of the frame are joined by steel galvanized plates and angles. Zinc screws for wood are used for mounting plates.
Node of a frame. Adjoining the rafters to the upper lining of the carcass of the second floor. To the upper binding of the rafters are attached with powerful angles and screws.
Mounting the grid on the rafters. On top of the cobbles will be laid OSB boards..
December.
The frame is ready, and there are rafters. Stacking OSB boards on the roof is underway. We try to put the OSB as quickly as possible to protect it from precipitation.
For ventilation pipes of galvanized steel with a diameter of 130 mm were used. The pipes were placed in a brick box. The comet tube 150 mm is located in the middle and is further insulated with mineral wool.
Node of installation of beams of overlap.
The inner surface of the walls is covered with a vapor barrier of reinforced polyethylene film. In the places of installation of radiators a skeleton of boards is provided.
Internal work was carried out in January-February (unfortunately, the photos were not preserved)
May
Exterior wall decoration vinyl siding under brick. The wall siding has been started with siding.
The process of lining the walls continues. The roof is covered with a layer of bituminous polymer Euroruberoid without splashes. Lining under the shingles of bitumen.
The roof is covered with bituminous tiles. Pipe over the roof frame. On a wooden frame will be screwed OSB board, inside a steel pipe, between the pipe and frame mineral wool insulation.
It looks like a house with a siding-lined pipe.
A fragment of a house with an erker.
General view of the house.
Now you know about building a turnkey house in the winter
About building a frame house with your own hands can be read HERE